Scope Creep Early Warning: Spotting Out-of-Scope Requests in Client Calls
How consultancies and professional services teams can spot out-of-scope requests in client calls early, log them before work starts and raise them calmly.
Scope creep rarely arrives as a formal request. It appears at the end of a call, as a question asked lightly: "while you're here, could you also take a look at...", or "would it be possible to add one more round before the board meeting?" The consultant says it is no trouble, the client thanks them, and the work begins. By the time the change shows up in an invoice dispute or a margin review, it has usually been done for several weeks, and nobody can say exactly when it started.
This article is about catching those requests while they are still visible. It covers what counts as scope creep, why client calls are where it usually begins, how to build a scope baseline that a team can check during a call, and how to log and raise an out-of-scope request without damaging the relationship. It is written for consultants, account leads, project managers and the finance staff who support them, in management consultancies, legal and accounting advisory practices, agencies and IT services firms.
Contract terms, change-control rules and commercial decisions belong to each firm. Any question about what an engagement letter requires, or how a change should be priced, should be taken to the firm's own advisers. Meetlytic's meeting records are one way to see the pattern of requests across calls, and they are described where they fit. The habits themselves work with any note-taking process.
What scope creep actually is
Scope creep is work that is added to an engagement beyond what was agreed, without a corresponding change to the fee, the timetable or the resources. The key word is unpriced. A client who asks for something new is not, by that fact alone, creating a problem. Clients' needs change, and a good advisory relationship should adapt to them. The problem arises when a change is absorbed without anyone deciding whether to absorb it.
It helps to separate three kinds of request, because each calls for a different response.
The first is a clarification of work that is already in scope. An example is a question about the format of an agreed deliverable, or about which of two stakeholders should receive a draft. This is normal, it should be answered promptly and it rarely needs a formal response.
The second is a change in the client's situation that really does require a different output. A regulator may move a deadline, a board may ask for a different level of detail, or a data source may become unavailable. This is a legitimate change, and it should be raised as one, with a discussion of effort, timing and fee before the work changes.
The third is a new piece of work that was never part of the agreement and that the client expects without paying for it. This is scope creep in the narrow sense, and it is the category this article focuses on. The client may not realise they are asking for something extra. The consultant may not realise that they have agreed to it.
The distinction matters because the response is different in each case. Clarifications should be answered quickly. Legitimate changes should be priced and agreed. Unpriced additions need a decision: the team does the work and records it as a deliberate choice, declines it, or agrees a change. What must be avoided is the silent fourth option, which is to do the work and say nothing to anyone who could decide about it.
It is also worth noting that some unpriced work is a deliberate business decision. A firm may choose to do a small piece of work for a valued client as a goodwill gesture, or to invest in a relationship that it expects to grow. That can be sensible. The difference is that a deliberate decision is made, recorded and understood by the people responsible for the engagement. Scope creep is what happens when the decision is never made at all.
Why client calls are where it starts
Most scope creep begins in conversation, because conversation is where expectations form. A call is friendly, the client is enthusiastic and the consultant wants to be helpful. The request sounds small, and saying yes feels like good service. Nobody is trying to take advantage. The request arrives in a form that does not trigger the usual checks, and the moment passes before anyone has looked at the plan.
Several features of client calls make this more likely. Requests often come from someone who was not part of the original scoping discussion, such as a new director or a colleague from another department, who has a reasonable need but no sight of what was agreed. Calls are short and crowded, with several topics in one hour, so a request can slip past without being written down. The request may be phrased as a question, which makes it sound like an enquiry rather than a commitment. And in many firms the person who hears the request is not the person who owns the budget, so the decision about whether to accept it is quietly deferred until it is too late to change.
Timing adds another pressure. Many engagements run to tight deadlines, and a consultant who has just missed a milestone may be keen to show flexibility. A client who is anxious about a board presentation may be more willing to ask for extra work. Neither situation is unusual, and both make it harder to hold a line in the moment without damaging the relationship.
The result is that the first trace of scope creep often lives in a sentence in the call notes, a line in a summary or an email that begins "as discussed". If the team does not look at these traces, the change stays invisible until it is expensive to reverse. The earlier a team learns to read these traces, the more options it has.
Building a scope baseline
A consultant cannot spot out-of-scope work during a call without knowing what is in scope. The first defence is a short, plain scope baseline that anyone on the team can read before a meeting. It does not need to be a legal document. It needs to answer a few practical questions, and it should be updated whenever the agreement changes.
The baseline should list the deliverables, with a short description of each and the date it is due. For a process review, for example, the list might name the current-state map, the options paper and the final report, with a note on what each contains. It should list the main assumptions, such as the number of stakeholders involved, the data the client will provide, the format of outputs and the people who will review them. It should state the number of review rounds included, the meetings expected and the people who are authorised to request changes.
Most importantly, the baseline should list the exclusions. These are the things the team has explicitly not agreed to do: for example, a second region, a separate vendor assessment or an update to the client's internal systems. Exclusions are often the most useful part of the baseline, because they make it obvious when a request falls outside the agreement. Many scope disputes turn on something the client assumed was included and the firm assumed was excluded. Writing the exclusions down removes most of that ambiguity.
A baseline might contain the following sections, written in plain language:
- Purpose of the engagement, in one or two sentences.
- Deliverables, with due dates and the reviewers for each.
- Assumptions about data, access, stakeholders and timing.
- Review rounds and meetings included.
- Exclusions, stated explicitly.
- People authorised to request changes, and how requests should be made.
- The process for raising a change, including who prices it and who approves it.
Keep the baseline where the team will see it before calls. A link at the top of the project channel, or a one-page document attached to the matter record, is enough. The aim is that a consultant joining a call on a Tuesday afternoon can see in seconds whether a request sounds like part of the plan, and who to speak to if it does not.
Signals to listen for in a call
Some out-of-scope requests have recognisable shapes. Listening for them is a skill, and it can be taught to a team using examples from its own work.
Certain phrases often signal an unpriced addition. These include "while you're at it", "it would be quick if you could", "just one more", "can you also look at" and "it would help us if". None of them is a problem in itself, but each is a cue to check the baseline before answering. Requests that bring in a new audience, such as a board, a regulator or a different business unit, also deserve attention, because they often imply new deliverables or a different level of detail.
Changes to the shape of the work are another signal. A request to move a deadline forward, change the format of an output, add a language version or include a new data source usually affects effort, even when it sounds minor. So does a request for a review round that was not included, or for a meeting the plan did not anticipate. A request to attend an internal session of the client's own team, to present to a wider audience or to explain the work to a new person is also worth checking, because it may take more time than it appears.
Watch for the phrase "we assumed". When a client says they assumed something was included, the gap between their assumption and the baseline is exactly the kind of misunderstanding a clear scope document prevents. The response is not to argue about the assumption on the call. It is to note it, check the baseline and clarify the position in writing.
Finally, listen to the consultant's own language. Phrases such as "I'll try to fit it in", "I can probably squeeze that in" and "let me see what I can do" suggest that the work is being absorbed without a decision. These are understandable habits, especially for people who want to be helpful, but they are the moments when a team should pause and check.
A checklist for the call itself might look like this:
- Is the request in the baseline, in the exclusions or neither?
- Does it change a deliverable, a date, a review round or a meeting count?
- Does it bring in a new person, audience or data source?
- Has anyone on the team already agreed to it informally?
- Who in the firm can decide whether it is accepted?
Following a thread across several calls
A single out-of-scope request is easy to handle. A pattern of small ones is harder, because each request looks reasonable on its own. A hypothetical example shows the problem.
An IT services firm agrees with a client to run a discovery workshop and produce a short written report for the client's operations team. In the second call, the client asks for a quick comparison of two software vendors, and the consultant agrees to add it as a favour. In the fourth call, the client asks for the report to be revised to include a second regional office. In the sixth call, the client asks whether the workshop could be repeated for the regional team, and the consultant says it should be manageable. Each request is modest. Together they represent a substantial amount of unpriced work that nobody has considered as a whole, and the account lead only realises the scale when the project is reviewed at the end of the quarter.
Seeing the pattern requires a record across meetings. A meeting history makes this possible. If each call is summarised and linked to the account, the team can search for a topic across several weeks and see how often it has come up. The article on following one account thread across many meetings describes how to read this kind of history. For scope creep, the useful question is simple: how many times has the client asked for something that is not in the baseline, and has anyone logged it?
One practical method is to tag each out-of-scope request with the deliverable it touches. In the example above, the vendor comparison touches no existing deliverable, the regional revision touches the report and the repeat workshop touches the discovery activity. Tagging makes it easy to see which parts of the engagement are attracting the most unpriced attention. It also shows whether a single deliverable is growing beyond its original shape, which is often the clearest early warning of scope drift.
A meeting record is also useful for telling the difference between a single favour and a trend. One request in a long relationship may be a sensible investment in goodwill. Several requests that each add effort to the same deliverable suggest that the scope needs to be reopened, and the team should say so before the next call. The record helps because the requests are visible in the order they were made, which is hard to reconstruct from memory later.
Responding during the call
The best response to an out-of-scope request in the moment is neither a refusal nor an immediate yes. It is a short, friendly acknowledgement that the request has been heard, followed by a clear next step. The consultant can say that the request sounds useful, that it is not in the current plan and that they will confirm the effect on timing and fees in writing. This buys time to check the baseline, speak to the engagement lead and offer options.
Some phrasing helps. A consultant might say: "That's a useful point, and I want to make sure we handle it properly. It isn't in the current plan, so I'll come back to you by the end of the week with what it would involve and whether it changes the timetable." The response is honest, specific and does not commit the team to anything. It also tells the client what will happen next, which reduces the chance that the client assumes the work is already agreed.
Consultants should avoid two common mistakes. The first is to agree to the work on the call and promise to sort out the paperwork later. This is the most common route into unpriced scope, because the paperwork rarely catches up with the work. The second is to give a firm refusal without offering a route forward. The client usually has a legitimate need, and a good response treats it as one. The question is how the need should be met, not whether the client is allowed to have it.
A short written note after the call is often the most useful step. It can say what was requested, confirm that the team will come back on it and name the person who will do so. It should not contain any commitment that the team has not yet checked. A note of this kind protects the consultant, reassures the client and creates a record that the request was noticed, which matters if the position is revisited later.
When the request is urgent, the consultant can ask for a short internal check before the call ends. Stepping out for a few minutes to speak to the engagement lead is often better than committing on the spot. Clients usually understand that a team which checks before agreeing is taking the request seriously.
Logging the request before work starts
Once a request has been noted, it should be logged. The log does not need to be complicated, and it can live in the same system as the meeting records. It should record the date and the meeting in which the request was made, the person who made it, a short description of what was asked, the team's estimate of the effort, the deliverables it affects and the decision that is needed. Where the request is linked to an action item from the call, the action should point to the log entry, so the two cannot drift apart.
A simple log entry might contain the following fields:
- Date of the request, and the meeting or channel it came from.
- Name of the person who made the request, and their role.
- A short description of what was asked, in the client's words where possible.
- The deliverables or activities affected.
- The team's initial view of effort and timing, marked as an estimate.
- The decision status: new, under review, agreed as a change, phased, declined or treated as goodwill.
- The name of the person who will decide, and the date by which a decision is expected.
The most important rule is that work on the request does not start until it has been decided. This may feel bureaucratic, especially when the request is small and the client is waiting. But the log protects the team as much as the client. A request that has been logged and agreed can be delivered with confidence. A request that was started informally can become a dispute about whether it was ever meant to be included, and that dispute is harder to resolve than a short delay in starting work.
Some firms allow exceptions, for example where a regulatory deadline or a safety issue makes delay unreasonable. Those exceptions should be defined in advance, recorded when they are used and reviewed afterwards. The point is not to prevent all flexibility. It is to make sure that flexibility is a decision rather than a habit, and that someone with authority has made it.
Logging also makes the status of each request visible. A request that has sat in "under review" for three weeks is a risk, because the client may believe it is being done. A regular look at the log, as part of the review described later, keeps pending items from being forgotten.
Options to offer the client
When a request is out of scope, the team has several options, and the client should be offered the ones that fit the situation. Presenting options is usually more productive than presenting a single price.
The first option is to add the work as a change. The team prices the additional effort, explains the effect on the timetable and asks for written agreement before starting. This is the clearest route when the request is important to the client and the team can deliver it. It also creates a formal record that the scope has changed, which protects both sides.
The second option is to swap the work. The client can agree to drop or defer an existing deliverable in exchange for the new one, so that the total effort stays within the agreement. This works well when the client's priorities have shifted and the original plan no longer fits. It is important to be clear about what is being removed, because a swap that is not recorded can leave the client believing that the original deliverable is still coming.
The third option is to phase the work. The new request is placed in a later stage of the engagement or in a separate follow-on piece, so that it can be planned and resourced properly. This suits requests that are valuable but not urgent. Phasing also gives the client a clear sense of when the work will happen, which often reduces the pressure to add it now.
The fourth option is to decline, with an explanation. This is sometimes the right answer, for example where the request would change the nature of the engagement or create a risk that the team is not prepared to take. A refusal that explains the reason and offers an alternative is usually better received than one that simply says no, and it is easier to defend later if the decision is questioned.
Finally, the firm may choose to do a small piece of work as a goodwill gesture. That can be a legitimate business decision, but it should be recorded as one, with the reason and the approval. What the firm should not do is treat a goodwill gesture as if it were in scope, or let it become a pattern that the baseline no longer describes.
Choosing between these options is a matter for the engagement lead, with input from the finance team where fees are affected. The consultant's job is to present the request accurately and to make sure the options are visible. The decision should not rest on a single person's view of what the client will tolerate.
Estimating the effort
A change is only as good as the estimate behind it. An estimate for an out-of-scope request does not need to be precise, but it does need to be honest, explained and checked. The team should be able to say what the estimate includes, what it assumes and how confident it is.
A practical approach starts with the baseline. The team considers the deliverable the request affects and asks what would change: the amount of analysis, the number of drafts, the number of people involved, the number of meetings and the time needed for review. Each change is then estimated in the same units the original plan used, whether that is days, hours or stages. Assumptions are written down, so that the client can see what they would need to provide for the estimate to hold.
An estimate should also state what it does not cover. A request for a comparison of two vendors, for example, may exclude any negotiation with those vendors, any technical testing and any follow-up workshop. Naming the exclusions prevents a small estimate from being read as a commitment to a much larger body of work.
The estimate should be reviewed by someone other than the person who made it. A second look often catches assumptions that are too optimistic, or effort that has been overlooked, such as the time needed to brief a new team member or to update a shared document. The review does not need to be lengthy. Its purpose is to make the estimate defensible, not to add layers of approval.
Where the firm has a standard way of pricing change requests, it should use it. Where it does not, the team should agree a simple method before the next change arises. An unpriced change is hard to discuss, and an agreed method makes it easier to explain the price to a client without reopening the question of whether the work is worth doing.
Keeping the meeting record accurate
Scope decisions depend on what was actually said. If the call summary records a request as "agreed" when it was only discussed, the team may later believe that a commitment exists that the client does not recognise. Summaries are useful for capturing requests, but they can also overstate or misstate them, especially when a tool has merged two points or turned a suggestion into an action.
Before a request is logged or a change is raised, the consultant should read the relevant part of the summary against their own memory and any recording the firm is entitled to use. The same care applies to action items. An action item that reads "send revised report to regional team" is a commitment, and the team needs to know whether the revision is in scope before it is treated as one. The article on turning meeting decisions into action items that get done describes how to keep actions clear enough to be checked.
A simple discipline helps. The summary should distinguish between three kinds of statement: a decision that was taken, a request that was made, and a suggestion that was discussed. Requests and suggestions are not commitments, and they should not be logged as agreed until the team has checked the baseline and made a decision. If a summary blurs these categories, the consultant should correct it before it becomes the basis for a change.
Consent and confidentiality also matter here. Recordings and summaries may contain information about several people, and the client may have restrictions on how meeting content is stored or shared. The consent and governance questions for meeting records should be settled before a team relies on them for commercial decisions. The article on consent, privacy and governance for meeting analytics sets out the points to consider.
Raising it without damaging the relationship
Clients rarely object to being told that a request is outside the plan. They object to discovering it on an invoice. The earlier and more openly a team raises scope, the less likely it is to feel like a dispute, and the more likely the client is to see the team as a partner in managing the work.
A good approach is to present the facts as a short list. The team writes a note to the client that sets out what was requested, what is already in the plan and what the options are. The note should not blame the client for asking, and it should not suggest that the team has been unfairly burdened. It should make the situation visible, so that the client can make an informed choice.
A short example of the structure, written generically, might read: "Thank you for the request on the second region. I want to make sure we plan it properly. The current plan covers the first region only, and the report is based on that scope. Adding the second region would affect the analysis, the review rounds and the timetable for the final report. I can set out what it would involve, with an estimate and the effect on dates, so that you can decide which option works best." The note is specific, calm and invites a decision, without any suggestion of wrongdoing.
Timing matters too. Raising a scope question in the same week as the request is usually easier than raising it at the end of a project. A note sent after several weeks of unpriced work can feel like a complaint, even when it is not intended as one. A note sent while the request is still new feels like an ordinary conversation about the plan.
The team should be ready to explain its own reasons. If the team is worried about the timetable, the quality of the work or the resources available, it should say so. Clients tend to respect candour, and a clear explanation of what the team can and cannot do is more useful than a vague apology. A conversation that begins with honesty about constraints usually ends with a more realistic agreement.
Finally, the tone should match the relationship. A long-standing client may accept a brief, informal note, while a new client or a more formal engagement may need a fuller written change request. The principle is the same in each case: the client should know what has been asked, what is in the plan and what decision is needed.
Early warning for the team
Beyond individual calls, a firm can watch for signs that scope is drifting across its portfolio. These signs are not verdicts on the people involved. They are prompts to look at a matter more closely before the position becomes harder to change.
Useful signals include a rise in time recorded against general or miscellaneous codes on a matter, which can indicate work that is not clearly tied to a deliverable. A growing number of logged requests that remain undecided is another signal, because it suggests that work may be proceeding without a decision. A pattern of review rounds that exceed the baseline is a third, and a fourth is a steady number of meetings that were not anticipated in the plan. Each of these, read together, can show that a matter is moving away from the agreed scope.
A short fortnightly review can help. The account lead or project manager reads the meeting summaries for each active matter, checks the log against the baseline and notes any requests that are pending. The review does not need to be long, and a checklist keeps it focused:
- Are there any new requests from the last two weeks, and has each been logged?
- Are any logged requests still awaiting a decision, and is anyone working on them?
- Has any deliverable grown beyond its original description?
- Are review rounds and meetings within the baseline?
- Have any assumptions been challenged, and are they still valid?
- Is there any goodwill work that should be recorded as a decision?
The purpose of the review is to make sure that decisions are being made, not to second-guess every conversation. Where a matter shows several signals at once, the lead should contact the engagement partner or equivalent, so that the client conversation can be planned before the situation becomes urgent.
Roles and escalation
Scope management works best when the responsibilities are clear. Each person in the process has a part to play, and problems tend to arise where one person assumes another has handled a request.
The consultant listens for signals, responds courteously in the call, notes the request and logs it. The account lead or project manager owns the baseline, reviews the log, prepares the estimate and drafts the client note. The engagement partner or senior lead decides whether to accept, phase, decline or treat a request as goodwill, and is responsible for the client conversation on significant changes. The finance or billing team applies the firm's pricing and approval rules, and it tracks the effect of agreed changes on the fee. Where the firm has a risk or quality function, it may review matters with a high volume of change requests.
Escalation should be simple. A request that is small, clearly within a deliverable and easy to price can usually be decided by the account lead. A request that changes the nature of the engagement, affects the fee materially or raises a risk should go to the engagement partner before anyone speaks to the client about it. A request that the client insists on, but that the firm is not willing to accept, should be discussed at the senior level, with the reasons recorded.
Writing these steps into a short page helps the team, and it helps the client too, because the client can see that changes are handled in a consistent way. The page does not need to be formal. It needs to be used.
Common mistakes to avoid
Several mistakes recur in engagements where scope creep becomes a problem. Recognising them makes it easier to avoid them.
The first is treating every request as a favour. Favours are sometimes appropriate, but when every request is handled informally, the baseline stops describing the work, and the team has no basis for a conversation later.
The second is relying on memory. A request made on a call that is not logged will be remembered differently by different people. The consultant may recall a small favour, the client may recall a commitment and the account lead may recall nothing at all. A log removes that ambiguity.
The third is waiting until the end of the project to raise the issue. A large amount of unpriced work at the end of an engagement is hard to discuss, and the client may feel that the firm has been hiding the problem. Earlier conversations are almost always easier.
The fourth is letting a single person carry the whole relationship. If one consultant is the only person who knows what has been agreed, the team is vulnerable when that person is ill, moves on or is replaced. A shared baseline and a shared log protect the engagement and the people in it.
The fifth is confusing a clear explanation with a defensive one. A note that sets out the baseline and the options is helpful. A note that sounds like a legal warning is not, and it can damage a relationship that the team would like to keep.
What the record cannot settle
A meeting record can show that a request was made, when, by whom and in what words. It cannot decide whether the request is within the contract. That depends on the engagement terms and on the law that applies to them, and it should be decided with the firm's own advisers. A record also cannot make a client accept a change, and it cannot replace a conversation about priorities.
Nor should every out-of-scope request be treated as a problem. Some requests are the start of a larger piece of work, and some are a sign that the client is getting more value from the relationship than the original plan anticipated. Those are good outcomes, and they should be recognised. The purpose of early warning is not to refuse everything that is new. It is to make sure that new work is noticed, discussed and decided, so that the team's time is used where it was intended and the client understands what it is getting.
A record also cannot tell a team whether a particular request is worth accepting. That is a judgement about the relationship, the firm's capacity, the commercial terms and the reputational value of the work. The record informs the judgement, but the judgement belongs to the people responsible for the engagement.
Closing thoughts
Scope creep is rarely a single decision. It is the sum of many small yeses, given in good faith during calls that were moving quickly. The defence is not to become less helpful. It is to make the scope visible before the call, listen for the signals that a request is unpriced, log what is asked, decide what to do before the work starts and raise the matter early and openly. Teams that do these things tend to have fewer disputed invoices and fewer difficult conversations at the end of a project, and they can give clients a clear view of what the engagement includes.
For teams that want to see how meeting summaries, action items and interaction history can support this kind of tracking, the Meetlytic features page describes how these pieces fit together. The decisions about scope, price and contract remain with the firm, and they should be taken with the firm's own advisers.
A worked example: one request, four decisions
The log and the options are easier to apply with a single request followed through. Consider a hypothetical management consultancy running a six-week review of a client's procurement process. The baseline covers an analysis of current supplier contracts, one options paper and one steering meeting. Supplier-level interviews are listed as excluded.
In a steering call in week three, the client's finance director asks whether the team could also interview the five largest suppliers, because the board wants evidence before it agrees the options. The consultant says the request is useful, that it is not in the current plan, and that the team will confirm what it would involve by the end of the week. A short note follows the call, naming the request and the person who will respond.
The account lead then checks the baseline and drafts an estimate. Five interviews, preparation, notes and a summary would take a defined amount of additional effort, and the review would need an extra week. The estimate is checked by a second person, who points out that the interview guide would need approval from the client's legal team. That dependency is added to the assumptions.
The engagement partner decides the response. The interviews are not refused, because the board's need is genuine. They are offered as a change, with the price and the extra week stated, and with the option to phase them into a follow-on piece if the client prefers to keep the current timetable. The partner also asks the finance director to confirm which interviews matter most, so that the estimate can be reduced if only three are needed.
The client chooses the change, in writing, with the extra week agreed. The log entry moves from "under review" to "agreed as a change", and the action item from the call points to that entry. Only then do the interviews begin. The example shows the sequence that matters: acknowledge, check, estimate, decide and agree in writing, before any work starts.
Frequently asked questions
What is the difference between a change request and scope creep?
A change request is a deliberate, priced change to the agreed work, usually raised by the client or by the team and agreed in writing before the work starts. Scope creep is work that is added without that agreement, so that effort grows without any change to fee or timetable. The difference lies in whether the change was decided, not in whether the client asked for something new.
Should a consultant agree to a small request on the spot?
A consultant can acknowledge the request on the spot, but should avoid committing to it until the team has checked the baseline and the effect on timing. A short response that says the request has been noted, and that the team will confirm what it involves, keeps the conversation friendly without creating an unpriced obligation.
How can a team spot scope creep across several meetings?
It helps to keep a meeting record for each account, with summaries and action items linked to the matter. Searching that history for repeated topics shows when a client has asked for similar work several times. Combined with a log of requests and the scope baseline, the pattern becomes easier to see before it reaches an invoice.
Does a meeting summary prove that a client agreed to something?
Not on its own. A summary can record a request as agreed when it was only discussed, or it can misstate a suggestion as a commitment. Before relying on a summary to show agreement, the consultant should check it against their own notes and any recording the firm is entitled to use, and the firm's advisers should decide how the record is treated under the engagement terms.