    Client Meeting Minutes and Sign-Off: Keeping an Agreed Record

    How consultancies can write client meeting minutes, confirm decisions with the client and keep a signed-off record of what was agreed.

    In client work, a meeting often ends with everyone leaving with a slightly different understanding of what was agreed. The sponsor remembers a firm go-ahead. The project lead remembers agreement in principle, pending a budget check. The client's finance team has no record at all. Weeks later the gap surfaces, when a deliverable is reviewed, an invoice is queried or a change request is challenged. The argument is then about what was said rather than what should happen next.

    Client meeting minutes, followed by a sign-off step, reduce that risk. The minutes set out what was decided and who agreed to do what, and by when. The sign-off confirms, in a form the firm can later show, that the client's representative accepts the minutes as an accurate record. Neither step is complicated, but both are easy to neglect when an engagement is busy, and both are easier to get right when the rules are agreed before the first meeting.

    This article explains how to write minutes that are useful to both sides, how to prepare for a meeting so that its decisions are easy to record, how to draft minutes from meeting records without losing accuracy, how to run the sign-off step and how to handle corrections and disagreement. It is written for engagement managers, project leads and the people who take minutes for them. It ends with two worked examples and a checklist that can be adapted to most engagements.

    Notes and minutes are not the same thing

    Working notes are what a consultant writes for the team during a meeting. They are full of shorthand, half-finished thoughts, reminders and opinions. They are valuable to the people who wrote them, and they should stay inside the team. A line such as "client seems unconvinced by option B, sponsor worried about the board" may be accurate and useful internally, but it should never reach the client.

    Minutes are a formal record shared with the client. They describe what happened in the meeting in a form that either party can rely on later. They are shorter than notes, more careful in their wording and more precise about decisions and actions. Someone who was not in the room should be able to understand what was agreed from the minutes alone, and an attendee should be able to confirm, quickly, that they are accurate.

    Keeping this distinction clear avoids two common problems. The first is sending working notes to the client, which exposes internal opinions and reads like a transcript. The second is keeping minutes so thin that they do not record the decisions at all. A useful test is to ask whether the minutes would let a new team member pick up the engagement without asking anyone what was agreed. If they would not, they are not yet doing their job.

    What minutes should contain

    Good client minutes follow a predictable structure, so that readers know where to find what they need. A practical set of sections is:

    • The meeting's purpose, date, time and location or call details.
    • The attendees, with their organisation and role, and anyone who sent apologies.
    • The decisions taken, each stated as a single clear sentence.
    • The actions agreed, each with an owner and a due date.
    • Open questions and items deferred to a later meeting, with the reason.
    • The date and time of the next meeting, and any papers that must be read beforehand.
    • The status of the minutes themselves: draft, issued or signed off, with a version number.

    The decisions and actions carry the most weight. They should be easy to find and should not be buried in the discussion. A reader who looks only at those two sections should understand what the team is now committed to doing. Place them near the top of the document, after the attendance, so that they are not missed.

    Keep the discussion section short. A summary of the main points raised is useful, particularly where it explains why a decision was taken, because the reasoning is often what the client will need to recall later. A blow-by-blow account of who said what is rarely helpful, and it makes the minutes harder to check. Two or three paragraphs are usually enough for a meeting of an hour.

    Be consistent in how you describe people. Use full names and roles at the first mention, and the same form thereafter. Where a person attended for only part of the meeting, say so. Where a decision was taken by a sub-group, name the group and its authority. Consistency makes the minutes easier to check, and it prevents the confusion that comes when the same person is described in three different ways across a project.

    An example of a well-formed decision

    Minutes are most useful when each decision can be read in isolation. Consider the following decision, written for a hypothetical steering meeting on a systems project. The steering group agreed to proceed with the revised data model, subject to the client's finance lead confirming the licence costs by the following Monday. The action to confirm the costs is recorded separately, with the finance lead as owner. The analysis lead will update the project plan within two working days of confirmation.

    Each element is there for a reason. The decision states what was agreed. The condition states what it depends on. The action names an owner and a date. The follow-on step shows what happens next. A reader who only sees the decision line will know the status is conditional, and a reader who sees the action will know who must act.

    Prepare the meeting so decisions are easy to record

    Most poor minutes are the result of poor preparation rather than poor note-taking. If the purpose of a meeting is vague, and the decisions it might take are not identified in advance, the minute-taker will struggle to separate decisions from discussion when the meeting is under way.

    Before a meeting with decisions to take, the engagement lead should prepare a short list of the decisions expected. For each decision, state the question, the options and the person who has the authority to decide. Circulate the list with the agenda. This does three things. It tells attendees which items require a decision. It gives the minute-taker a checklist to tick against during the meeting. And it creates a record that a decision was expected, which helps if the meeting closes without one.

    Ask the attendees to confirm their attendance and whether they can speak for their organisation. A steering group member who attends but cannot approve a budget change is a common source of later confusion. If the decision needs someone who is not present, the minutes should say so, and the item should be scheduled for a meeting that includes the right person.

    For hybrid and remote meetings, agree in advance how attendance will be recorded and how decisions will be confirmed. A person who joins by telephone for part of a meeting should be recorded as having attended for that part. A decision taken while a key participant has briefly dropped off should be checked with them before the minutes are issued. Many disagreements about minutes start with a decision that was made while someone was not fully present.

    Decide what counts as a decision

    Many disagreements about minutes come down to one word. A meeting can produce a decision, a recommendation, a suggestion, an agreement in principle or a request for further work. These are not the same thing. If the minutes blur them, the client may later treat a suggestion as an approval, or the firm may treat a tentative agreement as a firm go-ahead.

    Before the meeting ends, the chair should state each decision aloud, in the form it will appear in the minutes. For example, the chair might say, "The steering group has agreed in principle to move to phase two. Approval to proceed depends on the finance director confirming the budget by next Thursday." Everyone in the room then has the chance to correct the wording while the discussion is fresh. A decision that the chair cannot phrase in one sentence is probably not yet a decision.

    Be exact about the status of each item. A conditional decision should say what it depends on, and when the condition will be checked. A decision not yet approved by a named person should say who approves it and when. A recommendation should be recorded as a recommendation, with the decision it is intended to inform. An item the group did not reach should be recorded as deferred, not as agreed.

    This discipline also protects the consultant. When a client later asks why work started before budget confirmation, the minutes can show exactly what was agreed and what was still pending. The minutes may not settle the question, but they will show where the decision stood at the time, and that is usually what the conversation needs.

    Drafting minutes from meeting records

    Meetlytic produces meeting records, summaries, action items and insights from client conversations. These can make the drafting of minutes quicker, because the structure, attendees and action items are already captured. A draft from a meeting record is a starting point. It is not the finished minutes, and it should not go to the client in its raw form.

    The attendee who owns a decision or action should check the draft against their own memory and against the record. Check the attributions, because a draft can assign a comment to the wrong person. Check that the wording of each decision matches what was agreed, since a tentative remark can be presented as a firm decision. Check the dates, any figures, and the names and titles of the client's staff. The article on how to check an AI meeting summary before you share it sets out a review process that applies directly to minutes drafted from a summary, and it is worth reading before the first draft is produced.

    The rule for AI-drafted minutes is simple. The attendee who owns a decision or action checks it before the minutes go out for sign-off. The engagement owner is responsible for the document as a whole. No one should approve a line they have not read against their own understanding of the meeting. Where the draft is wrong, correct it, and keep a note of the correction in the working file so that the same error can be recognised next time.

    A short drafting checklist helps:

    • Has every decision been stated as one sentence, with its status?
    • Is each action paired with a named owner and a due date?
    • Does each attribution match the person who made the comment?
    • Are the attendees and their roles correct, including those who joined late or left early?
    • Do the dates, figures and document references match the source?
    • Have sensitive or internal remarks been removed from the version for the client?
    • Is the status and version number shown on the first page?

    Who owns what

    Clear roles prevent minutes from waiting in a queue or being approved by the wrong person. Four roles are usually enough for a client engagement.

    The author is the person who prepares the minutes. This is often a consultant or project coordinator, who uses the meeting record and the working notes to draft the document. The author does not decide what the decisions were; they record what the chair stated and what the attendees confirmed.

    The owner is the person in the firm who is accountable for the engagement and for the minutes being accurate. This is usually the engagement manager or project lead. The owner reviews the draft before it is sent, and decides whether the minutes are fit to issue.

    The client sponsor is the person on the client side who is responsible for the decisions in the minutes. They may not check every line, but they are the natural person to confirm that the minutes reflect what was agreed. Where a sponsor delegates the task, the delegation should be recorded.

    The action owners, on either side, are responsible for specific actions. Each of them should check the lines that concern them, because they are the people most likely to notice an error in their own commitments, and the people whose agreement the minutes will most affect.

    Decide these roles before the first meeting and write them into the kick-off material. It is much harder to agree who approves minutes after a disagreement has started, and the question tends to be decided by whoever is most insistent.

    The sign-off step

    Sign-off is an explicit confirmation by a named client representative that the minutes are an accurate record of the meeting. It is not the same as the client receiving the minutes, or failing to object to them. The distinction matters because a record that nobody has confirmed is weaker evidence than one that somebody has, and because silence is ambiguous in a way that a written confirmation is not.

    The form of sign-off depends on the firm, the client and the terms of the engagement. Some teams ask for a reply by email that says the minutes are agreed. Others use a signed document, or a formal approval step in a client portal. Some engagements use a combination: an email for routine minutes and a signed copy for decisions that carry financial or contractual weight. The method matters less than the clarity. Whatever the method, the minutes should say how they were confirmed, by whom and on what date.

    Set a sign-off window and state it on the minutes. For example, the minutes might say that the client is asked to confirm, or to propose corrections, within the window agreed at kick-off. The window should be realistic for the client's own review process. It should be agreed at kick-off, not invented each time, because a window that changes from meeting to meeting is hard to defend.

    Handle silence with care. If the client does not reply within the window, send a reminder that restates the decisions and asks for confirmation or corrections. Do not treat silence as acceptance unless the engagement terms say so. If the terms are unclear, take advice from whoever owns the contract, and show the status honestly. A set of minutes marked as issued but not yet confirmed is still useful, provided the status is clear to everyone who reads it.

    Once the minutes are signed off, file the approved version in the engagement folder and record the sign-off date in the index. Treat the approved version as fixed. Any later change should go into a new version, with its own change log.

    Sign-off across several client parties

    Some engagements involve more than one client representative whose agreement matters. A programme might have a sponsor, a finance lead responsible for budget and an operations director responsible for delivery. Each may have a stake in different decisions. In these cases, decide before the first meeting which decisions need which person's sign-off.

    One practical approach is to tag each decision with the person whose confirmation it needs. The sign-off request then names those people, and the status of each decision can be shown separately. A decision confirmed by the sponsor but not yet by the finance lead is still open for budget purposes, and the minutes should say so. A single sign-off for the whole document can hide that difference.

    Where the client's internal governance requires its own approval route, such as a formal board or committee approval, record that route in the minutes, along with the date by which the approval is expected. The firm should not describe a decision as approved by the client until the approving body has in fact approved it.

    Handling disagreement and corrections

    Separate two kinds of response from the client. The first is a factual correction, such as a wrong date, a misspelled name, a missing attendee or a wrong attribution. These should be fixed quickly and reissued. The second is a disagreement with a decision, such as a claim that the steering group never approved phase two, or that it approved it on a condition that was not recorded. This is substantive, and it should not be settled by editing the minutes.

    For a factual correction, issue a revised version with a version number, the date and a short change log that states what changed and why. Send it to everyone who received the original, so that no one is left working from a superseded copy. Never silently edit an issued version. Earlier drafts may already sit in other people's files, and a silent change makes it impossible to know which version a person relied on.

    For a disagreement, record the client's reservation in the minutes, and state what happens next. The minutes should be neutral. They should say that the client's representative does not agree with a particular decision, and give their reason in a sentence. Then place the decision on the agenda of the next meeting, with the relevant papers. The minutes of that later meeting should record the outcome and refer back to the earlier reservation. This keeps the record complete without pretending the disagreement did not happen.

    Where the disagreement concerns scope or fees, bring the minutes to the person who owns the contract before taking any further action. The minutes are evidence, and their status must be clear. A firm that acts on a disputed decision without checking the contract may weaken its own position, even where it is right on the facts.

    A worked example of a disputed decision

    Consider a hypothetical systems integration engagement. At a steering meeting in month four, the client's operations director asks to move the go-live date to the end of the quarter, to allow for user testing. The project lead believes the earlier date is still achievable if one module is deferred. No decision is reached.

    The minute-taker records the discussion without taking a side. The decisions section states that the go-live date was not agreed, and sets out both options. The earlier date, with one module deferred, is recorded with its stated risks. The later date is recorded with its stated effect on the budget. The minutes state that the decision will be taken at the next steering meeting, and that the operations director will circulate the testing plan beforehand.

    The project lead checked the wording of the module option, and the operations director checked the testing action. The client sponsor confirmed the minutes by email within the agreed window, and the email was filed with them. The sponsor's reply noted one correction, a misspelled name, which was fixed in a second version.

    At the next steering meeting, the client chose the later date. The decision was minuted with a reference to the earlier record. Later, when the client asked for an additional testing environment, the firm's change request cited the signed minutes, which showed that the testing period had been discussed and that its cost had been noted at the time. The record did not settle every question, but it showed what was discussed, what was pending and what had been approved.

    A second example of a sign-off that stalled

    Consider a different hypothetical engagement, in which a set of minutes was issued after a workshop with a client's operations team. The minutes recorded that the team had agreed a revised approval route for purchase requests. The client contact, a manager who had attended for part of the session, was the named sponsor, but the minutes were sent to the wider distribution list.

    No reply came within the window. The engagement manager sent a reminder, restating the single decision and asking for confirmation. Still no reply. Rather than treating the silence as acceptance, the engagement manager raised the item at the next steering meeting, where the sponsor confirmed the approval route and noted that the manager responsible for purchasing had not been consulted.

    The second set of minutes recorded the confirmation, the reason for the earlier delay, and the decision to add the purchasing manager to the distribution list for future sign-off. The episode cost a fortnight, but it prevented a decision from being implemented by people who had no part in it. It also showed the value of sending sign-off requests to the people whose agreement the decisions actually need.

    Version control and storage

    Minutes are only useful if people can find the right version. A simple convention helps. Use a consistent file name that includes the engagement, the meeting type, the date and the version number. Keep a single index for each engagement, listing each set of minutes, its status (draft, issued or signed off), its date and any reservations that were recorded.

    Store the approved minutes in the engagement's controlled folder, with access limited to the people who need it. Keep drafts separate, and make sure old drafts are not left in shared folders where they could be mistaken for the final version. A useful rule is that the only file in the signed-off folder should be the approved version, and drafts should be archived or deleted according to the firm's retention rules.

    Keep each client's material separate, so that minutes from one engagement cannot be sent to another client by mistake. This matters most for firms that work with several clients in the same sector, where similar project names and similar contacts can make a wrong send easy. Check the distribution list every time, not only the first time. Minutes can contain commercial figures, internal assessments of client staff and references to other clients, and a single misdirected message can cause real harm.

    The article on consent, privacy and governance for meeting analytics covers the wider principles for handling meeting material responsibly, including who may see a record and how long it should be kept.

    Retention and the archive

    Decide how long minutes will be kept, and write the decision down. The retention period may be set by the engagement terms, by professional obligations, or by the firm's own policy. It is not for the engagement team to decide alone. Once the period is set, apply it consistently, so that the archive is not left to grow indefinitely with material nobody needs.

    When an engagement closes, move the signed-off minutes and the index to the archive, with a note of the close date and the people who had access. Remove access for people who no longer need it. Keep drafts with the same care as final versions, because a draft can contain remarks that were removed from the final version, and those remarks may still matter in a later dispute.

    Using minutes to support change control

    Signed-off minutes can support change control, particularly where a steering group approves additional work or a change in scope. A minute that records an approval, with the approver's name and the date, is a clear basis for a change request. The same applies to a minute that records a request, the firm's response and the client's decision.

    Do not stretch minutes to show approvals that were never given. A discussion in which the client said the work would be useful is not an approval, and the minutes should not be written as if it were. If an approval is needed, record it as an approval. If it has not been given, record the request and its pending status, and say what the next step is. A reader should be able to see at a glance whether work is authorised.

    Check the firm's position on billing for additional work against the engagement terms and its accounting practice. Minutes are evidence of what was discussed and agreed. They are not, by themselves, a basis for invoicing, and the engagement owner should confirm the position before work that depends on a minute begins.

    Minutes for workshops and working sessions

    Not every client session is a formal meeting with decisions. A discovery workshop, a design review or a data validation session may produce ideas, options and open questions rather than decisions. These still need a record, but the minutes should be shaped differently. Write them as a record of outputs: what was discussed, what options were put forward, what was tested, and what was left open.

    A useful pattern is to separate three lists in the minutes. The first is decisions, which should be handled exactly as in a steering meeting. The second is options or proposals, each with a short description and the name of the person who put it forward. The third is open questions, each with an owner and a date by which the team expects an answer. This structure stops a workshop from producing an impression of agreement that the group never actually reached.

    Workshops also generate a great deal of material, such as flip-chart photographs, sticky notes and whiteboard sketches. Include only what the attendees need, and say where the rest is stored. A common mistake is to send the raw material as the minutes. Participants then have to interpret it themselves, and their interpretations will differ.

    Confirm the workshop minutes with the same discipline as any others, although the sign-off may be lighter. The client's workshop lead can often confirm the outputs quickly, while the decisions that follow from them may need a formal sign-off later. Make that split explicit, so that a participant does not assume the workshop outputs have been accepted as decisions when they have only been recorded as options.

    Checking minutes against the source

    Minutes drafted from memory are weak, and minutes drafted only from a summary are only a little better. Where a recording or transcript exists, and the engagement terms and the client's permissions allow its use, check the critical sentences against the source before the minutes are issued. The critical sentences are those that contain a decision, a condition, a deadline or a named commitment.

    This check does not need to be exhaustive. Most of the discussion will not matter for the minutes. A targeted check, which takes a few minutes per meeting, catches the errors that carry the most risk. Typical examples include a decision that was conditional but was summarised as firm, a date that was misheard, a figure that was rounded, and an action that was attributed to the wrong person.

    Where no recording exists, the check falls to the attendees. Ask each action owner to confirm their own action, and ask the chair to confirm the decisions. A short message that restates each decision and asks for confirmation is often enough. Keep the confirmations on file, because they form part of the evidence of what was agreed.

    Be cautious about using a recording to win an argument. A recording can settle a question about wording, but it can also reveal that everyone was speaking loosely and that the decision was less firm than anyone thought. The purpose of the check is to make the minutes accurate, not to show who was right. If the recording shows the decision was tentative, the minutes should say so.

    Remote, hybrid and multi-language meetings

    Client meetings are increasingly held with some attendees in the room and others on a call, and sometimes in more than one language. Each of these conditions adds risk to the minutes.

    For hybrid meetings, the minute-taker should record who attended in person and who attended remotely, and should note any period when a participant was not able to hear or see the discussion. A decision made while a remote participant could not hear it should be re-confirmed with them. The engagement owner should decide in advance whether remote attendees will be asked to confirm decisions separately, particularly where their organisation has a different approval route.

    Where a meeting is held in a second language, decide which language governs the minutes. The safest course is to draft and sign off in the language the decision makers use. If translation is needed, mark the translated text clearly, and say which version prevails if there is a difference. Do not assume that a translation will carry the same meaning as the original, particularly where the decision turns on a single word or a legal term. The client's own translator, where one is involved, is often the best person to check the key sentences.

    Remote attendance also affects the sign-off window. A remote participant who was on a poor connection may have missed part of the discussion, and they may need more time to review the minutes. Allow for this in the window, and say so in the minutes if an attendee's participation was partial.

    Minutes and the client's own records

    Clients keep their own records of engagements, and those records may differ from the firm's minutes. A client's internal board paper, its project log or its own meeting notes may describe a decision differently, or record a different date for it. Where this happens, the firm should not assume its minutes are right. Ask the client to explain the difference, and be prepared to correct the firm's own record if it is wrong.

    Sometimes the client's record is more accurate than the firm's, because the client's representative made a note of a condition the firm missed. Be open to that. The purpose of the minutes is to record what was agreed, and the firm's interest is in that record being right, not in its own version prevailing.

    Where the client's record and the firm's minutes differ on a point that matters, the engagement owner should raise the difference directly with the client's representative, in writing, and ask for it to be resolved. The resolution should be recorded, either as a correction to the minutes or as a note on the client's record. Leaving the difference unresolved is a risk, because it will surface later at a worse moment.

    Training the people who take minutes

    Minute-taking is a skill, and it is often given to the most junior person in the room. That can work, but only when the person is trained and supported. A short induction for minute-takers should cover the difference between notes and minutes, the way to phrase a decision, how to record a conditional outcome, how to handle a disagreement, and how to use the sign-off process.

    A useful practice is to review a sample of minutes at the end of each month, looking at the decisions and actions. Check whether decisions were stated clearly, whether owners and dates were recorded, and whether any sign-off was delayed by a drafting problem. The review should be supportive. The aim is to improve the next set of minutes, not to criticise the person who wrote the last set.

    Give the minute-taker the authority to ask the chair to restate a decision during the meeting. This is the single most effective way to prevent an unclear decision from reaching the minutes. A minute-taker who is afraid to interrupt will often produce minutes that the chair and the client later dispute.

    Common mistakes

    Sending minutes a week or more after the meeting is one of the most common problems. Minutes that arrive late are harder to check, because the client's memory has moved on and the discussion is no longer fresh. A practical target is to issue the draft for internal review promptly, so that the client receives it within a short period, while the meeting is still recent.

    Minutes that read like a transcript bury the decisions. The reader has to work out what was agreed from a long narrative, and the risk is that they will take the wrong meaning. Keep the discussion short, and keep the decisions and actions prominent.

    Leaving decisions buried in the discussion, so that a reader has to infer what was agreed, is a close relative of the transcript problem. Each decision should be stated as a decision, in its own line or paragraph.

    Accepting sign-off from someone who does not have the authority to confirm the decisions in the minutes is another frequent error. Check that the signatory is the right person, and record their role. A confirmation from a team member who cannot approve the decisions is not a confirmation of anything that matters.

    Editing minutes after sign-off without issuing a new version undermines the whole exercise. Even a small change should be made openly, with a version number and a change log. A silent edit, however well intended, makes the signed version unreliable.

    Finally, do not treat the minutes as a formality. They are the record that both sides will rely on when the engagement is reviewed, when a change is challenged or when a new team takes over the project. Minutes written with care at the time are far cheaper than an argument reconstructed from memory later, and the effort is small compared with the cost of the dispute they can prevent.

    A checklist for minutes and sign-off

    Before the meeting, the engagement lead should confirm the decisions expected, the people with authority to decide, the attendees and the mode of attendance. The sign-off window and the people who must confirm each decision should be agreed.

    During the meeting, the chair should state each decision aloud in one sentence, with its status. The minute-taker should note attendance changes, record the owners and due dates of actions, and flag any point that was unclear.

    After the meeting, the minute-taker should prepare a draft within a short period, and the owner of each action should check their own lines. The engagement owner should review the whole document and approve it for issue. The issued version should show its status, version number and sign-off window.

    When the client replies, the sign-off should be filed, recorded in the index and marked as the approved version. Any correction should be issued as a new version with a change log. Any disagreement should be recorded as a reservation and placed on the next agenda.

    At the close of the engagement, the signed-off minutes and the index should move to the archive, with access reviewed and retention applied as the firm has decided.

    Closing

    Client meeting minutes and a clear sign-off step give an engagement a shared record that both sides can rely on. They turn discussion into decisions, owners and dates, and they show which parts of the work are approved and which are still pending. The effort is modest, particularly when roles, the sign-off window and the distribution list are agreed at kick-off.

    If you want to see how meeting records, summaries and action items can support the drafting of minutes, Meetlytic provides these outputs from client conversations. You can contact the team to discuss how your firm handles client minutes today, or read the features overview to see what the platform covers.

    Frequently asked questions

    Are AI-drafted minutes ready to send to the client?

    No. A draft produced from a meeting record must be checked before it goes anywhere. The attendee who owns each decision or action should check their own lines against what they remember and what the record shows. The engagement owner should then review the document as a whole before it is issued.

    What is the difference between sending minutes and getting them signed off?

    Sending means the client has received the minutes. Sign-off means a named client representative has confirmed that they are an accurate record. Sign-off is the stronger evidence, because it shows that someone on the client side has accepted the content.

    What should happen if the client disputes a decision in the minutes?

    Separate factual corrections from disagreements. A wrong date or name should be corrected and reissued with a change log. A disagreement about a decision should be recorded as a reservation and placed on the agenda of the next meeting, and the later minutes should record the outcome. Do not settle a disagreement by quietly editing the issued version.

    Can signed-off minutes support a change request?

    They can, where they record a clear approval for additional work or a change in scope, with the approver's name and the date. They should not be stretched to show approvals that were never given. The firm's billing position should be checked against the engagement terms and its own accounting practice.